13-15标临电专项方案

来源:工作计划 发布时间:2020-09-15 点击:

 广州地铁二十一号线 5 15 标

  临电专项方案

  1

 目

  录 一、工程概况 ···································································································· 1

 二、编制依据 ···································································································· 1

 三、设备清单、线路负荷计算及选取导线截面 ·························································· 1

 3.1 镇龙站 ················································································································· 2

 3.2 存车线及项目部驻地 ······························································································· 3

 3.3 施工竖井 ·············································································································· 4

 3.4 中新站(盾构出口处) ······························································································ 4

 四、主干线路负荷计算,选取导线载面 ··································································· 5

 4.1 主要设备线路负荷计算收及导线截面选取 ···································································· 5

 4.2 盾构机线路负荷计算收及导线截面选取 ······································································· 7

 五、变压器的 的 选择 ····························································································· 8

 5.1 普通变压器的 选择 ································································································ 8

 5.2 盾构专用变压器的 选择 ························································································ 10

 六、各电箱开关的 的 选择 ······················································································ 10

 七 、漏电保护 ··································································································· 10

 八、供电系统配电方式 ······················································································· 10

 九、接地保护及防雷措施 ···················································································· 11

 9.1 接点保护 ············································································································· 11

 9.2 防雷装置 ············································································································· 11

 十、临时用电的 的 施工 ························································································· 12

 10.1 电缆及其附件选择 ······························································································ 12

 10.2 高低压配电盘(箱、柜)的 安装 ············································································· 12

 十一、临时用电平面布置图 ················································································· 13

 十二、盾构施工用电系统图 ················································································· 13

 十三、洞内高低压电缆敷设、盾构机高压电缆接头制作 ············································· 13

 13.1 电缆敷设 ·········································································································· 13

 13.2 电缆头制作 ······································································································· 13

 13.3 洞内高低压电缆及照明布置图················································································ 13

 十四、施工现场临时用电管理组织机构图 ······························································· 14

 十五、用电安全技术措施和电气防 火安全技术措施 ··················································· 15

 15.1 用电安技术措施 ································································································· 15

 15.2 电气防火安全技术措施 ························································································ 23

 十六、施工现场临时停电应急措施 ········································································ 25

 16.1 制定目的

 ········································································································· 25

 16.2 临时用电停电应急措施 ························································································ 25

 16.3 突发性停电的 应急措施 ······················································································· 25

 16.4 接到停电通知的 应急措施 ···················································································· 26

 十七、触电事故应急预案 ···················································································· 26

 17.1 应急措施 ·········································································································· 26

 17.2 应急物资 ·········································································································· 27

 十八、建立施工用电管理档案 ·············································································· 27

 附件:

 ············································································································ 28

 1 一、工程概况 广州市轨道交通二十一号线【施工 15 标】土建工程起讫里程为 YDK36+351.800~YDK38+398.000,线路全长约 2.046 千米。主要施工项目包括镇龙站(含通道、出入口、风道、风亭),镇龙站~中新站区间(含联络通道、施工竖井)土建工程,其中镇龙站采用明挖法施工,建筑总面积为 34887 米2;镇龙站~中新站区间左右线长分别为 1681.593米(长链 2.565 米)、1679.028 米,采用矿山法和盾构法施工。区间设置 2 座联络通道,在广汕公路北侧山脚(里程 YDK37+419.000)设置 1 处施工竖井。

 二、编制依据

  1、广州市轨道交通二十一号线工程图纸(镇龙站及区间);

 2、《建设工程施工现场供用电安全规范》

  GB50194—1993;

 3、《低压配电设计规范》

  GB50054—2011;

 4、《供配电系统设计规范》

  GB50052—2009;

 5、《通用用电设备配电设计规范》

  GB50055—2011;

 6、《建筑施工安全检查标准》

  JGJ 59-2011;

 7、《施工现场临时用电安全技术规范》

  JGJ46—2005; 三、设备清单、线路负荷计算及选取导线截面 本工程用电设备较多,采用需要系数法进行负荷计算。各设备的 主要参数通过查表取得,负荷计算见附表,电缆载流量对照表 3-1。

 为了保证工程的 顺利进行,现场设置 200KW 移动发电机一台,作为施工高峰期容量不足时的 备用电源或停电时工地照明、地下照明的 备用电源。

 表 3-1 聚氯乙烯绝缘电力电缆载流量 标称截面米米2

 非铠装 铠装 在空气中 在地下 在空气中 在地下 铜 铝 铜 铝 铜 铝 铜 铝 1.5 15 - 20 - - - - - 2.5 21 16 28 21 - - - -

 2 4 26 21 34 27 25 21 33 26 6 37 25 45 33 36 25 44 32 10 46 36 56 43 45 34 54 41 16 60 47 72 55 58 45 70 53 25 82 64 95 75 80 62 95 74 35 108 84 123 96 107 82 121 94 50 134 100 151 113 132 98 149 110 70 165 124 181 136 162 122 180 135 95 203 156 216 165 200 152 212 161 120 236 183 246 192 230 180 241 187 150 281 214 287 219 275 208 280 212 185 328 246 334 251 318 236 324 241 240 367 268 374 275 352 253 360 261 300 418 330 428 341 401 314 412 325

  1、本表适用于 0.6/1kv3+2 芯 4+1 芯 5 芯聚氯乙烯绝缘电力电缆载流量

  2、适用型号 VV,,VLV,,VV22,,VLV22,,,导电线芯最高工作温度 70℃

  3、空气温度 30℃,土壤温度 25℃,土壤热阻系数:1.2℃ 3.1 镇龙站

  表 3.1-1 镇龙车站设备、支路线截面选择 序 号 设备名称 数量 功率 KW/台 合计功率KW 导线载面积 1 钢筋调直机 1 5.5 5.5 VLV

 3x4+2x2.5 米米2

  2 钢筋切断机 1 3 3 VLV

 3x4+2x2.5 米米2

  3 钢筋弯曲机 1 3 3 VLV

 3x4+2x2.5 米米2

  4 空压机 2 7.5 15 VLV

 3x4+2x2.5 米米2

  5 水泵 5 30 150 VLV

 3x16+2x10 米米2

  6 45T 龙门吊 2 150 300

 VLV

 3x185+2x95 米米2

  7 砼喷射机 2 22 44 VLV

 3x10+2x6 米米2

 3 8 电焊机 2 30 60 VLV

 3x16+2x10 米米2

  9 双轴水泥搅拌2 150 300 VLV

 3x185+2x95 米米2

  10 砼振捣器 3 2.2 6.6 VLV

 3x4+2x2.5 米米2

  11 热风自动焊接2 30 60 VLV

 3x16+2x10 米米2

  12 塔吊 3 90 270 VLV

 3x95+2x50 米米2

  合计

 1217.1

  3.2 存车线及项目部驻地

  表 3.2-1 存车线和项目部驻地用电设备、支路线截面选择 序 号 设备名称 数量 功率 合计功率导线载面积 1 钢筋调直机 1 5.5 5.5 VLV

 3x4+2x2.5 米米2

 2 钢筋切断机 1 3 3 VLV

 3x4+2x2.5 米米2

 3 钢筋弯曲机 1 3 3 VLV

 3x4+2x2.5 米米2

 4 10T 龙门吊 1 50 50 VLV

 3x36+2x16 米米2

 5 电焊机 2 30 60 VLV

 3x16+2x10 米米2

 6 冲击钻机 4 75 300 VLV

 3x70+2x35 米米2

 7 双管旋喷桩2 150 300 VLV

 3x185+2x95 米米2

  8 砼振捣器 3 2.2 6.6 VLV

 3x4+2x2.5 米米2

 9 砂浆搅拌机 1 2.5 2.5 VLV

 3x4+2x2.5 米米2

 10 通风机 2 80 160 VLV

 3x70+2x35 米米2

 ∑1~10

 890.6

  11 1.5p 空调 47 1.3 61.1 BV

 4 米米2

 12 3P 空调 6 2.1 12.6 BV

 4 米米2

 13 饮水机 45 0.5 22.5 BV

 4 米米2

 14 笔记本 40 0.07 2.8 BV

 4 米米2

 4 15 打(复)印机 8 0.2 1.6 BV

 4 米米2

 16 照明 300 0.036 10.8

  BV

 2.5 米米2

 17 厨房设备 4 2 8 BV

 4 米米2

 18 电热水器 8 2 16 BV

 4 米米2

 19 电烧水器 2 2 4 BV

 4 米米2

 20 探明灯 2 0.28 0.56

 BV

 2.5 米米2

 21 视频监控 1 16.2 16.2 BV

 10 米米2

 ∑11~20

 156.16

 合计

 1046.76

  3.3 施工竖井

  表 3.3-1 施工竖井用电设备、支路线截面选择 序号 设备名称 数量 功率 合计功率导线载面积 1 钢筋切断机 1 3 3 VLV

 3x4+2x2.5 米米2

 2 钢筋弯曲机 1 4.5 4.5 VLV

 3x4+2x2.5 米米2

 3 电焊机 4 30 120 VLV

 3x16+2x10 米米2

 4 砼喷射机 1 22 22 VLV

 3x10+2x6 米米2

 5 空压机 2 75 150 VLV

 3x70+2x35 米米2

 6 通风机 2 80 160 VLV

 3x70+2x35 米米2

 7 提升设备 1 50 50 VLV

 3x35+2x16 米米2

 8 照明 1 30 30 VLV

 3x16+2x10 米米2

 9

 水泵

 2 30 60 VLV

 3x16+2x10 米米2

 10 10T 龙门吊 1 50 50 VLV

 3x35+2x16 米米2

 11 搅拌站 1 120 120 VLV

 3x120+2x70 米米2

 合计

 769.5

 5 3.4 中新站(盾构出口处)

  表 3.4-1 中新站(盾构出口处)用电设备、支路线截面选择 序号 设备名称 数 量 功率 合计功率导线载面积 1 钢筋切断机 1 3 3 VLV

 3x4+2x2.5 米米2

 2 钢筋弯曲机 1 4.5 4.5 VLV

 3x4+2x2.5 米米2

 3 电焊机 4 30 120 VLV

 3x16+2x10 米米2

 4 砼喷射机 1 22 22 VLV

 3x10+2x6 米米2

 5 空压机 2 75 150 VLV

 3x70+2x35 米米2

 6 通风机 2 80 160 VLV

 3x70+2x35 米米2

 7 10T 龙门吊 2 50 100 VLV

 3x35+2x16 米米2

 8

 水泵 4

  30 120 VLV

 3x16+2x10 米米2

 9 45T 龙门吊 2 150 300

 VLV

 3x185+2x95 米米2

  10 照明 1 30 30 VLV

 3x16+2x10 米米2

 合计

 1009.5

  四、主干线路负荷计算,选取导线载面 4.1 主要设备线路负荷计算收及导线截面选取

  计算公式:

 I 线 = (K ∑ ∑PC)/(1.732U 线 ×cos∮)

  I 线 —电流值(A)

  K ∑ —需要系数 ∑PC—容量 U 线 — 电压 cos∮—功率因数,取为 0.75

  4.1.1

 5 45 吨龙门吊:

 P 计 =K ∑ ∑PC=1×150 =150KW。(K ∑ 为需要系数,单台设备取 1)

 6 支线用电设备计算电流 I 线 =  cos 732 . 11000UP zc=75 . 0 380 732 . 1150 1000 =303.88(A) 支线总开关选择为:隔离开关为熔断式隔离开关 HR6-400/310,漏电开关选择为DZ20L-400/4300;额定漏电动作电流:100 米 A;动作时间:0.1S 查 3-1 电力电缆载流量表,支线电缆选为 VLV 3×185+2×95 米米2 电力电缆;相同或相近功率的 设备选择同规格电力电缆。

 0 4.1.2

 10 吨龙门吊:

 P 计 =K ∑ ∑PC=1×50 =50KW。(K ∑ 为需要系数,单台设备取 1) 支线用电设备计算电流 I 线 =  cos 732 . 11000UP zc=75 . 0 380 732 . 150 1000 =101.29(A) 支线总开关选择为:隔离开关为熔断式隔离开关 HR6-160/310,漏电开关选择为DZ20L-160/4300;额定漏电动作电流:100 米 A;动作时间:0.1S 查 3-1 电力电缆载流量表,支线电缆选为 VLV 3×35+2×16 米米2 电力电缆。

 4.1.3 搅拌站:

 P 计 =K ∑ ∑PC=120 =120KW。(K ∑ 为需要系数,取 1) 干线用电设备计算电流 I 线 =  cos 732 . 11000UP zc=75 . 0 380 732 . 1120 1000 =243.1(A) 干线总开关选择为:隔离开关为熔断式隔离开关 HR6-250/310,漏电开关选择为DZ20L-250/4300;额定漏电动作电流:100 米 A;动作时间:0.1S 查 3-1 电力电缆载流量表,支线电缆选为 VLV 3×120+2×70 米米2 电力电缆。

 4.1.4

 冲击钻机:

 P 计 =K ∑ ∑PC=1×75 =75KW。(K ∑ 为需要系数,取 1) 干线用电设备计算电流 I 线 =  cos 732 . 11000UP zc=75 . 0 380 732 . 175 1000 =151.94A) 干线总开关选择为:隔离开关为熔断式隔离开关 HR6-160/310,漏电开关选择为DZ20L-160/4300;额定漏电动作电流:100 米 A;动作时间:0.1S 查 3-1 电力电缆载流量表,支线电缆选为 VLV 3×70+2×35 米米2 电力电缆;相同

 7 或相近功率的 设备选择同规格电力电缆。

 4.1.5

 塔吊:

 P 计 =K ∑ ∑PC=1×90=90KW。(K ∑ 为需要系数,单台设备取 1) 支线用电设备计算电流 I 线 =  cos 732 . 11000UP zc=75 . 0 380 732 . 190 1000 =182.32 (A) 支线总开关选择为:隔离开关为熔断式隔离开关 HR6-250/310,漏电开关选择为DZ20L-250/4300;额定漏电动作电流:100 米 A;动作时间:0.1S 查 3-1 电力电缆载流量表,支线电缆选为 VLV 3×95+2×50 米米2 电力电缆;相同或相近功率的 设备选择同规格电力电缆。

 4.1.6

 生活用电主干线:

 P 计 =K ∑ ∑PC=1×156.16 =156.16KW。(K ∑ 为需要系数,照明回路取 1) 支线用电设备计算电流 I 线 =  cos 732 . 11000UP zc=75 . 0 380 732 . 116 . 156 1000 =316.36(A) 支线总开关选择为:隔离开关为熔断式隔离开关 HR6-400/310,漏电开关选择为DZ20L-400/4300;额定漏电动作电流:100 米 A;动作时间:0.1S 查 3-1 电力电缆载流量表,支线电缆选为 VLV 3×185+2×95 米米2 电力电缆;相同或相近功率的 设备选择同规格电力电缆。

 4.1. 7

 左、右线通风机: :

 P 计 =K ∑ ∑PC=1×80 =80KW。(K ∑ 为需要系数,单台设备取 1) 支线用电设备计算电流 I 线 =  cos 732 . 11000UP zc=75 . 0 380 732 . 180 1000 =162.07(A) 支线总开关选择为:隔离开关为熔断式隔离开关 HR6-250/310,漏电开关选择为DZ20L-250/4300;额定漏电动作电流:100 米 A;动作时间:0.1S 查 3-1 电力电缆载流量表,支线电缆选为 VLV 3×70+2×35 米米2 电力电缆;相同或相近功率的 设备选择同规格电力电缆。

 4.2 盾构机线路负荷计算收及导线截面选取 单台盾构机掘进时用电设备计算(SjS 单台)

 8 K ∑ =取为 1.05 SjS 单台=PjS 单台/COS∮

 取功率因数 COS∮=0.85 SjS 单台=PjS 单台/COS∮=1678.5/0.85=1974.07KVA I 线 = (K ∑ ∑PC)/(1.732U 线×cos∮) K ∑ =取为 1.05 I 线 = (1.05×1974.07)/(1.732×10×0.85)=140.79(A) 查电力电缆载流量表,由于线路较长考虑选择盾构机高压电缆为 YJV3×70+1×35米米2 电力电缆。

 五、变压器的 的 选择 5.1 普通变压器的 的 选择 1 5.1.1 镇龙站

 根据表 3.1-1 镇龙站设备(按 94“建筑安全”推荐公式)进行施工用电总量估算:

  S(KVA)=K(K 1 K 2 ∑P 1 /ηcoaα+∑P 2 K 3 ) 式中 S—工地用电量 KVA

  K—备用系数,取 1.05

  ∑P1—工地动力设备的 额定输出功率总和 KW,

 (其中 1 个 90KW 的 塔吊用电联结到存车线 630KVA 变压器)

  ∑P2—工地照明设备用电总和 KW,(联结到存车线 630KVA 变压器)

 η—动力设备平均效率,取 0.85

 coaα—电源功率因数,平均取 0.8

 K 1 —全部动力同时使用系数,取 0.7

 K 2 —动力负荷系数,取 0.75

 K 3 —照明设备同时使用系数,取 0.9

 1、∑P 1 =1217.1-90

  2、P 2 =0

 S 总 =1.05(1127.1×0.7×0.75/0.85×0.8+0×0.9)=584.77KW 按照最大 用电量选择变压器根据用电量计算,选容量为 630KVA 的 变压器。

  2 5.1.2 存车线及项目部驻地

 9 根据表 3.2-1 存车线设备(按 94“建筑安全”推荐公式)进行施工用电总量估算:

  S(KVA)=K(K 1 K 2 ∑P 1 /ηcoaα+∑P 2 K 3 ) 式中 S—工地用电量 KVA

  K—备用系数,取 1.05

  ∑P1—工地动力设备的 额定输出功率总和 KW,

 (其中含有镇龙站 1 个 90KW 的 塔吊用电联结到存车线 630KVA 变压器)

  ∑P2—工地照明设备用电总和 KW,

 η—动力设备平均效率,取 0.85

 coaα—电源功率因数,平均取 0.8

 K 1 —全部动力同时使用系数,取 0.7

 K 2 —动力负荷系数,取 0.75

 K 3 —照明设备同时使用系数,取 0.9

 1、∑P 1 =890.6+90

  2、P 2 =156.16

 S 总 =1.05(890.6×0.7×0.75/0.85×0.8+156.16×0.9)=609.64KW 按照最大 用电量选择变压器根据用电量计算,选容量为 630KVA 的 变压器

  3 5.1.3 施工竖井

 根据表 3.3-1 存车线设备(按 94“建筑安全”推荐公式)进行施工用电总量估算:

  S(KVA)=K(K 1 K 2 ∑P 1 /ηcoaα+∑P 2 K 3 ) 式中 S—工地用电量 KVA

  K—备用系数,取 1.05

  ∑P1—工地动力设备的 额定输出功率总和 KW,

  ∑P2—工地照明设备用电总和 KW,

 η—动力设备平均效率,取 0.85

 coaα—电源功率因数,平均取 0.8

 K 1 —全部动力同时使用系数,取 0.7

 K 2 —动力负荷系数,取 0.75

 K 3 —照明设备同时使用系数,取 0.9

 1、∑P 1 =769.5-30

 2、P 2 =30

 S 总 =1.05(739.5×0.7×0.75/0.85×0.8+30×0.9)=440.37KW

 10 按照最大 用电量选择变压器根据用电量计算,选容量为 630KVA 的 变压器

  4 5.1.4 中新站(盾构出口处) )

 根据表 3.2-1 存车线设备(按 94“建筑安全”推荐公式)进行施工用电总量估算:

  S(KVA)=K(K 1 K 2 ∑P 1 /ηcoaα+∑P 2 K 3 ) 式中 S—工地用电量 KVA

  K—备用系数,取 1.05

  ∑P1—工地动力设备的 额定输出功率总和 KW,

  ∑P2—工地照明设备用电总和 KW,

 η—动力设备平均效率,取 0.85

 coaα—电源功率因数,平均取 0.8

 K 1 —全部动力同时使用系数,取 0.7

 K 2 —动力负荷系数,取 0.75

 K 3 —照明设备同时使用系数,取 0.9

 1、∑P 1 =1009.5-30

  2、P 2 =30

 S 总 =1.05(979.5×0.7×0.75/0.85×0.8+30×0.9)=536.54KW 按照最大 用电量选择变压器根据用电量计算,选容量为 630KVA 的 变压器 5.2 盾构专用变压器的 的 选择 根据负荷计算及厂家提供资料,每台盾构机的 额定功率为 1678.5kw,因此每台盾构机选用一台容量为 2000KVA 移动式开关站。

 六、各电箱开关的 的 选择 根据各路电流的 大 小 ,各电箱的 开关选择如《用电系统图》所示。

 七、漏电保护 总配电箱中漏电保护器的 额定漏电动作电流应大 于 30 米 A,额定漏电动作时间应大 于 0.1S,但其额定漏电动作电流与额定漏电动作时间的 乘积不应大 于 30 米 A·s。开关箱中漏电保护器的 额定漏电动作电流不应大 于 30 米 A,额定漏电动作时间不应大 于 0.1S。

 建筑施工现场第三级配电箱内必须装设漏电保护器,其额定漏电动作电流应大 于

 11 配电线路和用电设备总泄漏电流值的 二倍以上。建筑施工现场临时用电应形成两级以上的 漏电安全保护网。本工地施工现场总配电箱中,严格将动力用电和照明用电分开设置。动力用电和照明用电均装设总漏电保护器。

 八、供电系统配电方式 供电系统采用低压链式、放射式与树干式相结合的 配电方式。

 九、接地保护及防雷措施 9.1 接点保护 采用 TN-S 系统(TN-S 系统的 中性线 N 和保护线 PE 始终严格分开,所有设备的 外露可导电部分均与 PE 线相连,TN-S 供电系统中,在总配电箱、供电线路终点及每一个建筑物的 进户线中的 PE 线都必须作重复接地,但 N 线不宜重复接地)。

 见下 TN-S 系统图 L1 L2 L3 N PE PE

 PE TN-S 系统图 各用电设备、配电箱、柜接地电阻要求小 于 4 欧姆,每个接地级采用 20×1800 米米圆钢。

 9.2 防雷装置 防雷装置由外部防雷装置和内部防雷装置两大 部分组成;外部防雷装置由接闪器、引下线、接地装置组成,外部防雷装置能起到拦截雷电,并将部分雷电流引入大 地中泄放的 作用。内部防雷装置,由防雷等电位连接等组成,在建筑物内电气系统和电子系统需要防雷时,还应考虑采取屏蔽和电气、电子系统的 进一步等电位连接、合理布线等措施。

 阻止雷电电磁感应的 有效手段之一是屏蔽,在建筑物墙体中金属及金属门窗等,

 12 通通连起来,形成“笼”状,就可以将雷电电磁场挡在“笼”之外了。

 防御雷电反击最有效的 办法之一是做等电位连接:将建筑物的 金属、门窗的 金属部分、设备的 金属外壳和所有平时不带电的 金属物体,通通就近接到同一接地装置上,使它们成为等电位体。

 在配电室的 架空进线处应将绝缘子铁脚与配电室的 接地装置相连接,施工现场内的 起重、井字架、龙门架等机械设备,以及钢脚手架和正在施工的 在建工程等的 金属结构,当在相邻建筑物、构筑物等设施的 防雷装置接闪器的 保护。

 十、临时用电的 的 施工 10.1 电缆及其附件选择 10.1.1 进洞高压电缆选择

 盾构机与地面高压开关站的 连接,采用不带铠装的 YJV3×70+1×35 米米2 交联电缆作为进洞高压电缆。

 10.1.2 终端头、中间接头选择

 户外地面开关站均选用热缩型终端头和冷缩型终端头,从实际效果看,选用热缩型终端头技术可靠、经济合理。进洞高压电缆中间连接方式可选用以下三种:1.采用热缩型中间接头。2. 采用冷缩型中间接头。3. 采用一进一出高压分支箱。我单位从成本、安全、操作的 角度 综合考虑,采用热缩型中间接头。

 10.2 高低压配电盘(箱、柜) 的 安装 10.2.1 配电柜

 低压配电柜到达施工现场后就位前,应检查配电柜是否符合施工组织设计和施工现场的 实际要求。内安装的 配电柜应在土建相应工作结束以后进行。

 2 10.2.2 配电柜 的

 基础

 配电柜的 基础槽钢一般为 8~10 号槽钢,槽钢应先调直和除锈后安装。

 3 10.2.3 成套柜 的

 安装应符合下列要求:

 ① 机械闭锁、电气闭锁应动作准确、可靠。

 ② 动触头与静触头的 中心线应一致,触头接触紧密。

 ③ 二次回路辅助开关的 切换点应动作准确,接触可靠。

 13 ④ 配电盘、箱、柜内的 电气元件应完整无损,参数调整符合要求。

 ⑤ 配电盘、箱、柜的 接地应牢固可靠,装有电器的 活动盘、柜门,应用软导线与接地的 金属构架可靠接地。

 10.2.4 高压部分 的

 验收

 高压柜及其高压电缆的 在完成后做单项专门验收。

 十一、临时用电平面布置图 二十一号线施工 15 标临时用电平面布置图(见附图一) 十二、盾构施工用电系统图 二十一号线施工 15 标施工用电系统图(见附图二)

 十三、洞内高低压电缆敷设、盾构机高压电缆接头制作 13.1 电缆敷设 (1)确认敷设路线,水平路线确定包括水平预埋弯钩,电缆弯接处理等。垂直路线包括地面与基坑电缆竖井的 连接。确定敷设路线时,应了解洞内设备情况及盾构机推进情况,作业道路是否畅通,为电缆敷设和牵引做好准备。

 (2) 洞内高压电缆分两部分,一部分是悬挂在管片上的 交联电缆,另一部分为设置盾构机台车电缆盘上。

 13.2 电缆头制作

 (1) 热缩型电缆中间接头制作流程:

 13.3 洞内高低压电缆及照明布置图 十四、施工现场临时用电管理组织机构图

  项目经理王宁作为项目的 第一负责人也是安全第一负责人,对本项目的 安全工作全面负责。

 安质部长王方瑞为安全责任具体管理人,负责日常的 安全管理工作,贯彻执行相

 14 关法规,保障项目部安全符合规定,掌握本项目部的 安全情况。为本单位的 安全提供必要的 经费和组织保障。

 专职安全员张建强对现场安全负责,认真学习贯彻“预防为主”的 工作方针,组织实施上级的 有关文件。

 对本项目部的 职工进行经常性的 安全知识教育和培训工作。组织开展安全生产应急演练工作。纠正违反安全的 行为,并向安全管理人提出处理意见。对所属项目部的 安全工作进行经常性的 检查,及时消除安全隐患。

 十五、用电安 全技术措施和电气防火安全技术措施 15.1 用电安技术措施 (1) 总则 ① 本措施根据 GB 50194—93“建设工程施工现场供用电安全规范”,结合盾构机掘进工程的 特点制定。

 ② 建设工程施工现场供用电的 安全、可靠,除执行本措施外,尚应符合国家现行有关标准、规范的 规定。

 (2) 发电、变电、配电设施 ① 发电设施 a. 自备发电机应放在龙门吊工作范围内,便于运输和线路引出方便 。

 b. 柴油发电机组应停放在高出周围地面0.25-0.3米的 平面上,该平面的 排水坡度 不应小 于 0.5%。

 c. 柴油发电机组上部应设防雨棚,防雨棚应牢固、可靠。

 d. 柴油发电机组的 出口侧应装设短路保护、过负荷保护及低电压保护等装置,发电机和外电线路系统变压器之间应当互锁。

 ② 变压设施、配电设施 a. 变压柜、配电柜区不受洪水冲浸、不积水,地面排水坡度 不小 于 0.5%。

 b. 门向外开,其高度 与宽度 便于设备出入。

 c. 变压器的 引线与电缆连接时,电缆及其终端头,均不应与变压器外壳直接接触。

 d. 采用箱式变电站供电时,其外壳应有可靠的 保护接地。接地系统应符合产品技术要求:装有仪表和继电器的 箱门,必须与壳体可靠连接。

 e. 箱式变电站安装完毕或检修后,经供电局检查验收后合格,交付我方使用。

 (3) 架空配电线路及电缆线路

 15 电缆敷设 ① 供电电缆应沿道路路边或建筑物边缘敷设;转弯处和直线段每隔 20 米处应设电缆走向标志。

 ② 电缆直埋后嗣,其表面距地面的 距离不宜小 于 0.2~0.7 米;电缆上下应铺以软土或砂土,其厚度 不得小 于 100 米米,并应盖砖保护。

 ③ 电缆与铁路、厂区道路交叉处,应敷设在坚固的 保护管内;管的 两端宜伸出路基

  2 米。

 ④ 低压电缆(不包括油浸电缆)需架空敷设时,应沿建筑物、构架物架设,其架设高度 不应低于 2.7 米;接头处应绝缘良好,并应采取防水措施。

 ⑤ 电缆直埋时,电缆之间,电缆与其他管道、道路、建筑物等之间平行和交叉时的 最小 距离应符合规定。严禁将电缆平行敷设于管道的 上方。特殊情况应按下列规定执行:

 电力电缆间、控制电缆间以及他们互相之间在交叉点前后 1 米范围内,当电缆穿入管中或用隔板隔开时,其交叉距离可减为 0.25 米。

 ⑥ 进入变电所、配电所的 电缆沟或电缆管,在电缆敷设完成后应将管口堵实。

 (4) 接地保护及防雷保护 ① 接地保护 a.施工现场设有专供施工用的 低压侧为380/220V中性点直接接地的 变压器,其低压侧应采用保护导体和中性导体分离接地系统(TN-S 系统)。

 b. 接零保护应符合下列规定: 1) 接引至电器设备的 工作零线与保护零线必须分开。保护零线上严禁装设开关或熔断器. 2) 保护零线和相线的 材质应相同,保护零线的 最小 截面应符合下表的 规定.

  保护零线最 小

 截面

 相线截面(米米2 ) 保护零线最小 截面(米米2 ) S≤16 S 16<S≤35 16 S>35 S/2 3) 接引至移动式电动工具或手持式电动工具的 保护必须采用铜芯软线,器界面不宜小 于相线的 1/3,且不得小 于 1.5 米米2 . c. 用电设备的 保护地线或保护零线应并联接地,并严禁串联接地或接零.

 16 d. 保护地线或保护零线应采用焊接、压接、螺栓连接或其它可靠方法连接。严禁缠绕或钩挂。

 e. 低压用电设备的 保护地线可利用金属构件、钢筋混凝土构件的 钢筋等自然接地体,但严禁利用输送可燃液体、可燃气体或爆炸性气体的 金属管道作为保护地线。

 ② 防雷保护 a. 广州的 年平均雷暴日数是 81.3(d/a),高于 20 米的 机械设备要安装避雷装置,在本工程使用的 所有设备中,都没有高于 20 米的 机械设备,所以不需要安装避雷装置。

 (5) 常用电气设备 ① 一般规定 a. 采用的 电气设备应符合现行国家标准的 规定,并应有合格证件,设备应有铭牌。

 b. 使用中的 电气设备应保持完好的 工作状态,严禁带故障进行。

 i. 电气设备不得超铭牌运行。

 ii. 固定电气设备应标志齐全。

 ② 配电箱和开关箱 a. 配电箱和开关箱应安装牢固,便于操作和维修。

 b. 落地安装的 配电箱和开关箱,设置地点应平坦并高出地面,其附近不得堆放杂物。

 c. 配电箱、开关箱的 进线口宜设在箱的 下面或侧面,电源的 引出线应穿管。

 d. 照明、动力合一的 配电箱应分别装设刀闸和开关。

 e. 配电箱、开关箱内安装的 接触器、刀开关等电气设备,应动作灵活,接触良好可靠,触头没有烧蚀现象。

 ③ 熔断器和插座 a. 熔断器的 规格应满足被保护线路和设备的 要求;熔体不得削小 或合股使用,严禁用金属线代替熔丝。

 b. 容体应有保护罩,管型融体器不得无关适用;由填充材料的 融体器不得改装使用。

 c. 熔体熔断后,必须查明原因并排出故障后方可更换;装好保护罩后方可送电。

 d. 更换熔体时严禁采用不合规格的 熔体代替。

 e. 插销和插座必须配套使用。I 类电气设备应选用可接保护线的 三孔插座,起保护端应与保护地线或保护零线连接。

 ④ 移动式电动工具和手持式电动工具 a. 手持式电动工具的 管理、使用、检查和维修,应符合现行国家标准《手持式电动工

 17 具的 管理、使用、检查和维修安全技术规程》的 规定。

 b. 长期使用或新领用的 移动式电动工具和手动式电动工具在使用前应进行检查,并应测绝缘。

 c. 移动式电动工具、手持式电动工具应加装单独的 电源开关和保护,严禁一台开关接两台或两台以上电动设备。严禁将电动工具的 外壳接地线和工作零线拧在一起插入插座,必须使用两线带地或思念线带地插座,或者将外壳接地线单独接到接地线上,以防接触不良时引起外壳带电。专供接零保护的 芯线上不许有工作电流通过。

 d. 移动式电动工具、手持式电动工具通电前应做好保护接地或保护接零。

 e. 移动式电动工具的 用软电缆连接移动设备时,电源开关应采用双刀开关控制,其开关应安装在便于操作的 地方。

 f. 移动式电动工具、手持式电动工具当采用插座连接时,其插头、插座应无损伤、无裂纹,且绝缘良好。

 g. 使用移动式电动工因故离开现场暂停工作或遇突然停电时,应拉开电源开关。

 h. 移动式电动工具和手持式电动工具,应加装高灵敏动作的 漏电保护器。

 i. 移动式电动工具和手持式电动工具的 电源线,必须采用铜芯多股橡套软电缆或聚乙烯绝缘氯乙烯护套软电缆。电缆应避开热源,且不得拖拉在地上。当不能满足上述要求时,应采取防止重物压坏电缆等措施。

 j. 移动式电动工具和手持式电动工具工作时需要移动时,不得手提电源线或转动

 部分。

 k. 移动式电动工具和手持式电动工具使用完毕后,必须在电源侧将电源断开。

 l. 使用手持式电动工具应戴绝缘手套或站在绝缘台上。

 ⑤ 电焊机 a. 根据施工需要,电焊机宜按区域和标高层集中设置,并应编号。

 b. 布置在室外的 电焊机用设置在干燥场所,并应设棚遮蔽。

 c. 电焊机的 外壳应可靠接地,不得多台串联接地。

 d. 电焊机各线圈对电焊机外壳的 热态绝缘电阻值不得小 于 0.4 米Ω。

 e. 电焊机的 裸露导电部分和转动部分应装安全保护罩。直流电焊机的 调节齐被拆下后,机壳上露出的 孔洞应加设保护罩。

 f. 电焊机一侧的 电源线必须绝缘良好,不得随地拖拉,其长度 不宜大 于 5 米。

 g. 交流电焊机械应安装防二次侧触电保护器

 18 h. 电焊机的 的 电源开关应单独设置。直流电焊机电源应采用启动器控制。

 i. 电焊把钳必须绝缘良好。

 j. 电焊机二次侧引出线宜采用橡皮绝缘铜芯软电缆,其长度 不宜大 于 30 米。

 ⑥ 起重机 a. 起重机电气设备的 安装,硬度 和现行国家标准《电气装置安装工程起重机电气装置施工及验收规范》的 规定。

 b. 起重机电源电缆的 长度 应符合产品技术要求。

 c. 轨道式起重机自动卷线装置动作必须灵活可靠;电缆不得在地上拖拉。

 d. 轨道式起重机电源电缆收放通道附近及清洁,不得对放其他设备、材料和杂物。

 e. 中、小 型起重机上或其附近,应设能断开电源的 开关。

 f. 起重机写的 电源电缆应经常检查,并设专人维修。

 g. 未经有关人员批准,起重机上的 电气设备和接线方式不得随意改动。

 h. 起重机上的 电气设备应定期检查,发现缺陷应及时处理,在起吊过程中不得进行电气检修工作。

 i. 起重机电气设备的 检修和试运行,必须取得其他专业人员的 配合。

 j. 轨道式起重机轨道两端,应各设一组接地装置,当轨道较长时,每隔 20 米应加装一组接地装置。

 (6) 特殊环境 ①

 易燃、易爆环境 a. 施工现场供用电电器设备及电力线路的 选型和安装,应符合现行国家标准《爆炸和火灾环境电力装置设计规范》及电气设置安装工程爆炸和火灾危险环境电气装置施工及验收规范》的 规定。

 b. 照明灯具应选用防爆型,导线应采用防爆措施。

 c. 严禁带电作用,更换灯泡时应短开电源。

 d. 电气设备正常不带电的 外露导电部分,必须接地或接零。保护零线不得随意断开,当需要断开时,应采取安全措施,工作完结后应立即恢复。

 ② 特别潮湿环境 a. 在特别潮湿的 环境中,电气设备、电缆、 导线等,应选用封闭型或防潮型号。

 b. 电气设备金属外壳、金属构架和管道均应接地良好。

 c. 移动式电动工具和手提式电动工具,应加装漏电保护器或选用双重绝缘设备。长期

 19 使用的 电动工具,使用前应测绝缘。

 d. 行灯电压不得超过 12V。

 e. 潮湿环境不得带电作业,一般作业应穿绝缘靴或站在绝缘台上。

 (7) 照明 ① 照明灯具和器材必须绝缘良好,并应付和现行国家有关标准的 规定。

 ② 照明线路应布线整齐,相对固定。是内安装的 固定式照明灯具须按挂不得低于 2.5米,室外安装的 照明灯具不得低于 3.0 米,安装在露天工作场所的 照明灯具应选用防水型灯头。

 ③ 现场办公室、宿舍、工作棚内的 照明线,除橡套软电缆和塑料护套线外,均应固定在绝缘子上,并应分开敷设;穿过墙壁时,在竹木脚手架上应加绝缘子,在金属脚手架上应设木横担和绝缘子。

 ④ 照明电源线路不得接触潮湿地面,并不得接近热源和直接绑挂在金属构架上。在脚手架上按装临时照明时,在竹木脚手架上应加绝缘子,在谨慎脚手架上应设木横担和绝缘子。

 ⑤ 照明开关应控制相线。当采用螺口灯头时,相线应接在中心触头上。

 ⑥ 使用行灯应符合下列要求:

 a. 电压不得超过 36V。

 b. 盾构机有 24V 交流电压。

 c. 行灯应有保护罩。

 d. 行灯的 绝缘受柄应绝缘良好且耐用、防潮。

 e. 行灯的 电源线应采用橡套软电缆。

 f. 行灯变压器必须采用双绕组型。

 ⑦ 变电所及配点所内的 配电盘、配电柜及母线的 正上方,不得安装灯具(封闭母线及封闭式配电盘、配电柜除外)。

 ⑧ 照明灯具与易燃物之间,应保持一定的 安全距离,普通灯具不宜小 于 300 米米;聚光灯、碘钨灯高热灯具不宜小 于 500 米米,且不得直接照射易燃物。当间距不够时,应采取隔热措施。

 (8) 安全技术管理 ① 供用电设施投入运行前,用电单位应建立、健全用电管理机构,组织好运行、维护专业班组,明确管理机构和专业按组的 职责。

 20 ② 用电单位应建立、健全安全供用电设施的 运行及维护操作规定:运行及维护人员必须学习这些操作规定,熟悉本单位的 供用电系统。

 ③ 用电单位必须建立用电安全岗位责任制,明确各级安全负责人。

 ④ 用电设施的 运行及维护人员必须具备以下条件:

 a. 经医生检查无妨碍从事电气工作病症。

 b. 掌握必要的 电气知识。考试合格并取得合格证书。

 c. 掌握触电解救法和人工呼吸法。

 ⑤ 用电单位的 运行及维护人员,必须学习和熟悉本规范的 有关规定,并应每年考试一次。因故断工作 3 个月以上者,必须重新学习本规范,并经考试合格后方可恢复电气工作。

 ⑥ 新参加工作的 电工、临时工、实习人员,上岗前必须经过安全教育,考试合格后在正式电工的 带领下,方可参加指定的 工作。

 ⑦ 变电所(配电所)内必须配备足够的 绝缘手套、绝缘杆、绝缘垫、绝缘台等安全工具。

 ⑧ 供电设施的 运行及维护,必...